NOTE 3: CONSTRUCTION IN PROGRESS

v3.3.1.900
NOTE 3: CONSTRUCTION IN PROGRESS
3 Months Ended
Mar. 31, 2015
Property, Plant and Equipment [Abstract]  
Property, Plant and Equipment Disclosure [Text Block]
NOTE 3: CONSTRUCTION IN PROGRESS

Construction in progress of $3,212,944 as of March 31, 2015 consists of costs incurred related to the construction of a 2-ton/hour test plant in Oklahoma. The total cost of the project, including testing to take place at a designated site in Oklahoma, is estimated at $6,400,000 plus an additional $750,000 to move the plant to its permanent location. In May, 2015, the company secured adequate financing to complete the fabrication of the test facility and moved it to the testing site at AES in Oklahoma in September, 2015. In quarter four 2015, the test plant was commissioned and testing of the plant started. It is expected that testing will continue until March, 2016 when the company will move the plant to a permanent location.