NOTE 4: CONSTRUCTION IN PROGRESS

v3.3.0.814
NOTE 4: CONSTRUCTION IN PROGRESS
12 Months Ended
Dec. 31, 2014
Property, Plant and Equipment [Abstract]  
Property, Plant and Equipment Disclosure [Text Block]
NOTE 4: CONSTRUCTION IN PROGRESS

Construction in progress of $3,212,944 and $3,200,473 as of December 31, 2014 and 2013 consists of the first payments made during February 2013 of $2,000,000 and additional costs incurred through March, 2014 related to the construction of a 2-ton/hour test plant in Oklahoma. The total cost of the project, including testing to take place at a designated site in Oklahoma, is estimated at $6,000,000. Commissioning of the coal testing plant is expected during the fourth quarter of 2015.