Quarterly report pursuant to Section 13 or 15(d)

NOTE 3: CONSTRUCTION IN PROGRESS

v2.4.0.8
NOTE 3: CONSTRUCTION IN PROGRESS
9 Months Ended
Sep. 30, 2013
Disclosure Text Block Supplement [Abstract]  
Other Assets Disclosure [Text Block]
NOTE 3: CONSTRUCTION IN PROGRESS

Construction in progress of $2,349,500 as of September 30, 2013 consists of the first payment made during February 2013 of $2,000,000 and additional costs incurred through September 30, 2013 related to the construction of a 2-ton/hour pilot plant in Oklahoma. The total cost of the project, including testing to take place at a designated site in Oklahoma, is estimated at $4,500,000. Commissioning of the pilot plant is expected during the fourth quarter of 2013.