Quarterly report pursuant to Section 13 or 15(d)

NOTE 3: CONSTRUCTION IN PROGRESS

v2.4.0.8
NOTE 3: CONSTRUCTION IN PROGRESS
6 Months Ended
Jun. 30, 2013
Disclosure Text Block Supplement [Abstract]  
Other Assets Disclosure [Text Block]
NOTE 3: CONSTRUCTION IN PROGRESS

Construction in progress of $2,016,800 as of June 30, 2013 consists of the first payment made during February 2013 of $2,000,000 and additional costs incurred through June 30, 2012 related to the construction of a 2-ton/hour pilot plant in Oklahoma. The total cost of the project, including testing to take place at a designated site in Oklahoma, is estimated at $4,500,000. Commissioning of the pilot plant is expected during the third quarter of 2013.